Structural and Fabric Restoration at 55 Wilton Street, Glasgow
Delivering Structural Recovery Under Pressure
Major tenement restoration completed on time despite extensive variation and structural complexity.
Client
Glasgow City Council
Duration
Oct 2024 – Jun 2025
Value
£660k
Type
Structural & Fabric Restoration
Overview
EBS Construction was appointed to deliver a comprehensive internal and external restoration of a four-storey, 19th-century sandstone tenement in Glasgow’s West End. The building had suffered extensive deterioration, including water ingress, decayed masonry, failing windows, and widespread rot across both common and private areas.
The works involved major structural repairs alongside full renewal of the building fabric to restore the property to a safe and maintainable condition.
The Challenge
Ongoing scope changes increased delivery complexity throughout the project.
A narrow lane required uninterrupted pedestrian and vehicle access.
Our Approach
Planning Coordination
Proactive engagement with the Planning Department helped streamline approvals and maintain momentum.
Traditional Materials
Use of traditional materials including slate, lime mortar, sandstone, and cast iron
Structural Solutions
Value-engineered structural solutions reduced risk and improved efficiency without compromising quality.
Programme Management
Detailed programme control allowed variations to be absorbed without delaying completion.
Stakeholder Communication
Transparent communication supported stakeholders and helped plan for successful reoccupation.
Key Challenges Solved
Maintaining Access
Bespoke scaffolding was designed to maintain uninterrupted pedestrian and vehicle access, including emergency routes.
Managing Change
Scope variations were incorporated through flexible planning and strong commercial control.
Structural Repairs
Strengthening works to walls, floors and staircases were delivered using optimised, approved solutions.
“Flexibility, control, and commercial awareness under changing conditions.”
Results
15 000+
Man-Hours
Completed with zero lost-time incidents.
On Time
Delivered safely with zero lost-time incidents.
£100,000+
Savings
Cost savings achieved for the client.
High-quality workmanship recognised by stakeholders.
Project Complete
Outcome for the Client
The building was returned to a stable, safe and maintainable condition, enabling residents to reoccupy without delay. The works significantly improved structural integrity, weather resistance and long-term performance.